Work in progress!
We have re-thought the project and the disabled veterans' toilet upgrade has become phase 1, the first of three phases which will comprise our complete toilet refurbishment. We have sufficient funding for phase 1 to be completed and work commenced on 22nd June.
Day 0, this was the starting point, to convert existing two stalls into one stall with an accessible toilet.
Day 2 and the partition and most of the old fittings have been removed, a new soil pipe and the framework for panelling in the pipework is in place.
Day 5 and the panelling has been completed.
Day 7 and the floor covering has been installed.
Day 8 and the wall cladding is finished, just waiting for the delivery of the accessible toilet suite (photo courtesy Denise Brady).
Day 10 - it's getting there!
Day 14 - complete with just a few cosmetic additions to be added. Thank you everyone!